YOUR FEE MONEY AT WORK
The Bureau of Land Management (BLM) started work on the BLM portion of Ogilby Road (just east of the tower) on Monday Feb. 8, 2010.

The goal is to make a one-lane passable dirt road over the soft spot by Friday afternoon, Feb. 12.

They will work on it all week as traffic allows. If too many RVs and OHVs arrive to the area thereby causing unsafe heavy equipment work, the BLM will have to stop before Friday.

Our hope is that they will finish before then.

To help the BLM to meet their Friday afternoon, Feb. 12 deadline, Ogilby campers are asked to hold off entering the area as long as possible on President's Day weekend.